top of page
Writer's pictureErin B.

December 2023 Justice Center Expansion Update


justice center

In the December 21 Justice Center Expansion meeting, the commissioners spoke with the new project manager, aka the BOCC's “Buyer’s Representative,” David Mendez and general contractor Bouten Construction about subcontractor bid packages in Work Package 3. All bid packages were opened and listed during the public meeting. According to the June 2023 work schedule, Bouten is a week ahead of schedule for bid packages although we still do not have an updated total cost estimate.

 

Schedule

 

Mendez updated the BOCC on Dec. 26 that they should have an updated cost estimate by the 2nd week of January.

 

Current total estimated expansion cost is $39.8M, $5 million higher than the estimate was at the June 26, 2023 meeting.


 The construction was divided into three subsections to help speed up the process, as seen on this presentation from the June 26, 2023 meeting.

June 2023 Work Packages

 

Updated Work Package Costs vs. Original Estimate


December 2023 Running Total

Original estimate from June 2023

Notes

Work Package 1

$5,108,638

$5,544,203


Work Package 2

$8,453,544

$18,786,737

Original WP2 included structure, mechanical, electrical, roofing, DFH, framing and drywall. As seen in the itemized list below it looks like half of WP2 was included in the updated WP3.

Work Package 3

Unknown due to WP2 changes, will have updates 2nd week of January.

$10,502,907



 

Justice Center Expansion Owner's Representative Clarification

The commissioners gave their “Buyer’s Representative,” David Mendez approval to make financial decisions up to $25,000 on behalf of the board for the justice center expansion with the understanding that the protocol is to immediately notify the board after that decision. Mendez was recently contracted to be the Justice Center Construction Manager on behalf of the BOCC after the board interviewed multiple candidates to help stop the financial bleeding happening with that expansion. Mendez will now be able to quickly make construction decisions on behalf of the board without having to wait for the next business meeting.

 

 

Bouten opened subcontractor bid packages for Work Package 3. Itemized bids below.

 

Bid package 15 Casework

Candela Construction $442,364.30

Pacific Cabinets Inc. $720,672

Beck Cabinet Co. $599,611

Advanced Custom Cabinets $486,175

TMI Systems Corporation $675,690 (this bid was read at 12/26 business meeting)

 

 

Bid package 16 Metal Panels

Axiom Construction and Consulting $424,950

Alternate #1 – 460,000

Alternate #2 - $28,425

 

Kilgore Architectural Products - $458,500

Alternate #1 – N/A

Alternate #2 - $76,500

 

Icon Corp - $607,800

Alternate #1 - $542,000

Alternate #2 - $30,000

 

FlemBEC - $609,000

Alternate #1 - $529,000

Alternate #2 - $46,000

 

Krueger Sheet Metal Company - $718,960

Alternate #1 – N/A

Alternate #2 - $119,800

 

 

Bid package 17 Roofing

Axiom Division 7 $465,700

Alternate #1 – 14,000

Alternate #2 - $19,000

 

Icon Corp $542,000

Alternate #1 - $5,000

Alternate #2 - $26,000

 

FlemBEC - $529,000

Alternate #1 - $56,000

Alternate #2 - $17,000

 

Jimmy’s Roofing - $468,300

Alternate #1 - $3,752

Alternate #2 – deduct $58,494

 

 

Bid Package 18 EIFS

All Wall Contracting Inc - $583,000

Alternate #1 - $225,445

 

 

Bid Package 19 Doors, Frames & Hardware

Bouten Construction $549,678

  


Bid Package 20 Overhead Coiling Doors

Continental Door Co - $116,003

Dupree Building Specialties - $154,933

 


Bid Package 21 Glazing

All Star Glass Co - $1,017,000

Modern Glass Co - $1,425,256

C&S Glass - $802,300

 


Bid Package 22 Drywall/Framing/Insulation

All Wall Contracting - $2,259,360

Alternate #1 - $563,000

Alternate #2 - $198,714

Alternate #3 - $15,200

 

LAC Drywall - $2, 398,000

Alternate #1 - N/A

Alternate #2 – N/A

Alternate #3 - $6,200

 

Performance Contracting Inc - $2,116,799

Alternate #1 – N/A

Alternate #2 – N/A

Alternate #3 - $25,099

 

Modern Drywall $2,026,000

Alternate #1 – N/A

Alternate #2 – N/A

Alternate #3 - $12,000

 

 

Bid Package 23 Acoustical Ceilings

Performance Contracting Inc - $314,142

Noise Control of WA - $299,774

On the Level Solutions LLC - $314,000

 

 

Bid Package 24 Flooring

IBEX Flooring - $823,972

Alternate #1 – deduct $27,855

 

Great Floors - $711,539

Alternate #1 - deduct $66,595

 

 

Bid Package 25 Painting

All Wall Contracting $202,250

Alternate #1 – N/A

 

Performance Contracting Inc - $453,449

Alternate #1 – $18,700

 

River City Painting of Spokane - $184,965

Alternate #1 – $9,040

 

S&S Coatings Inc - $277,900

Alternate #1 - $14,000

 

 

Bid Package 26 General Works

Bouten Construction - $1,042,962

 

 

Bid Package 27 was cancelled

 

 

Bid Package 28 Plumbing

Mackin & Little Inc - $1,179,736

ETCO Services LLC - $953,000

 

 

Bid Package 29 HVAC

ACI Northwest - $2,146,000

Alternate #1 - N/A

 

 

Bid Package 30 Electrical

McKinstry - $2,861,520

Alternate #1 - $207,165

Alternate #2 - $6,423

 

Peterson Electric - $2,897,000

Alternate #1 - $160,000

Alternate #2 - $9,000

 

Innovative Electrical Solutions - $2,381,920.96

Alternate #1 - $230,426.85

Alternate #2 - $N/A

 

Energized Electric - $2,890,000

Alternate #1 - $58,959

Alternate #2 - $2,692

 

 

Bid Package 31 Landscaping

Creekside Landscape - $112,300

Hidden Rivers Irrigation & Landscaping Inc - $99,800

Clearwater Summit Group Inc - $81,000

 

 

Bid Package 32 Site Concrete

Five Star Concrete - $63,820

Liberty Concrete - $85,979

Cameron Riley LLC - $78,110

 

Full video below or livestreamed here.



32 views0 comments

Recent Posts

See All

Comments


bottom of page